Skip to content
Close Menu
The Concho Observer
  • Advertise
  • Contact
  • News
  • Opinion
  • Drought and Weather
  • Business Directory
  • SUMMER FUN
Facebook X (Twitter) Instagram
Trending
  • Next Week is High Noon for Big Powerline Foes
  • Drug Operation Nets 24 in San Angelo Sweep
  • Angelo State Announces Rodgers Award Winners
  • Kids Eat Free with San Angelo ISD Summer Meals
  • First U.S. Screwworm Case Confirmed in S. Texas
  • Council Approves $2.35M Fire Truck, Reviews Capital Plan
  • Ballinger’s KRUN-AM Signs-Off After 79 Years
  • Data Developer Arrives At Commissioners Court
Facebook Instagram TikTok
The Concho Observer
Subscribe
Friday, June 5
  • Advertise
  • Contact
  • News
  • Opinion
  • Drought and Weather
  • Business Directory
  • SUMMER FUN
The Concho Observer
Home » SWIFT Fund Nearly $3 Billion Short of Demand
Environment

SWIFT Fund Nearly $3 Billion Short of Demand

Texas TribuneBy Texas TribuneMay 8, 2026Updated:May 8, 2026No Comments5 Mins Read
Facebook Email Copy Link
The Texas Water Development Board awarded $33,500,000 to Alliance Water for a new water treatment plant and pipeline segments in 2025 to serve Hays, Caldwell, Guadalupe, Comal, and Bexar counties. This year, 10 water projects received initial approval to split $1.28 billion in state money, but 13 others didn’t make the cut — including one that may supply drought-stricken Corpus Christi.
Share
Facebook Twitter LinkedIn Pinterest Email
Twin Mountain Fence

TEXAS TRIBUNE

By Colleen DeGuzman

As Texas struggles to meet the needs of a rapidly growing population, a state fund had $1.28 billion available this year to support projects that could deliver water even in a severe drought. 

Unfortunately, 23 worthy projects requested a total of $4.2 billion, prompting the state to deny 13 of them — the first time the SWIFT fund had to say no to an applicant in its 11-year history.

It was lamentable timing for a state plagued by a brutal drought and aging water infrastructure.

Webb, Stokes & Sparks Personal Injury Law

“We have more demand than we actually have the capacity to fulfill this year,” said Marvin Cole-Chaney, director of program administration and reporting for the Texas Water Development Board, which administers SWIFT, the State Water Implementation Fund for Texas.

One of the denied projects is a desalination plant with the potential to create 100 million gallons of drinking water a day along the Coastal Bend in South Texas — an area including Corpus Christi, which is in the grips of a devastating drought.

The denial surprised John Byrum, executive director of the Nueces River Authority, which proposed building the plant as a critical source of water for Coastal Bend cities. 

Under the scoring system used to set priorities for SWIFT, the river authority’s plant ranked 11th. The top 10 proposals will next submit more-detailed applications for the money. 

“We really thought our project would rate higher,” Byrum said. “We were disappointed.” 

The river authority requested $140 million to fuel plans to build a seawater desalination plant in Harbor Island, which sits within the cities of Aransas Pass and Port Aransas. A desalination plant filters salt and other minerals out of seawater to make it drinkable.

The proposed project, which received federal permitting in September and is projected to cost $3.2 billion, would distribute water to cities, water districts and businesses across South Texas, including Corpus Christi, which is nearing a water crisis. The coastal city is one of the biggest water suppliers in the region and may be just months away from a water crisis as its main reservoirs have shriveled to below 8% capacity. 

Corpus Christi paid $2.7 million to the river authority to reserve an option to buy 50 million gallons of water a day once the Harbor Island desalination plant is running.

City leaders are bracing for a Level 1 water emergency, the point when the water supply is projected to be 180 days from falling short of demand, which could be triggered as soon as September. Commissioners in Nueces County, which includes Corpus Christi, voted unanimously last week to declare a county-wide water emergency, restricting residents’ outdoor watering. 

SWIFT offers low-interest loans with extended and flexible repayment plans. The water development board said the denied projects may be eligible for other funding options, such as the Drinking Water State Revolving Fund, but Byrum believes the SWIFT fund should place a higher priority on an area’s need for water.

The water development board considers several factors when prioritizing projects, ranking them on a scoring sheet with a maximum score of 86. Projects can earn the most points by serving large populations, with readiness and water conservation among other factors also taken into account. 

A project’s “emergency need” carries little weight, earning a maximum five points.

None of the 10 highest-ranked projects earned any points for “emergency need,” a designation restricted to public water systems where supply is expected to fall short of demand within 180 days, federal money was sought or received to deal with the emergency, or the need for water will occur a decade sooner than anticipated by state planners.

The Harbor Island plant, despite targeting an area that critically needs water, earned no emergency need points and lost potential points because it is in rural Nueces County with a relatively low population. Its score of 62 was just one point behind the 10th-place project. 

This year’s 10 highest-rated SWIFT projects span the state, including the Riverbend Water Resources District — the top-rated project on the SWIFT scorecard. Riverbend is seeking $2.98 million to assess and expand water infrastructure to meet Texarkana’s growing population.

The North Texas Municipal Water District is asking for nearly $419 million for a pipeline and treatment plant in Leonard, a town in Fannin County. The water district is also receiving around $611 million to design a new raw water pump station. 

Money is also being directed to South Texas, where the Hidalgo County Drainage District made a pitch for $120 million for its proposed Santa Cruz Reservoir. 

Byrum said the Nueces River Authority is going to apply for the water board’s other funding programs, as well as seek private funding, in hopes of getting the Harbor Island desalination plant built. 

SWIFT was created by the Texas Legislature and approved by voters in 2013, allowing the one-time transfer of $2 billion from the state’s rainy day fund. Revenue bonds over the next 50 years, starting in 2015, will finance around $27 billion in water supply projects through SWIFT. 

To date, the water development board has committed about $17.2 billion in SWIFT money to 76 projects. The agency estimates the funding saved entities almost $2.1 billion over the life of the debt compared to market rates.

This article first appeared on The Texas Tribune.

Share this:

  • Email a link to a friend (Opens in new window) Email
  • Print (Opens in new window) Print
  • More
  • Share on Pinterest (Opens in new window) Pinterest
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Threads (Opens in new window) Threads
  • Share on Reddit (Opens in new window) Reddit
  • Share on Nextdoor (Opens in new window) Nextdoor
  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Share on Bluesky (Opens in new window) Bluesky
  • Share on Tumblr (Opens in new window) Tumblr

Like this:

Like Loading…
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Texas Tribune

Related Posts

Next Week is High Noon for Big Powerline Foes

June 5, 2026

Drug Operation Nets 24 in San Angelo Sweep

June 4, 2026

Angelo State Announces Rodgers Award Winners

June 4, 2026

Leave a ReplyCancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Subscribe to Our Weekly Newsletter

This is our main newsletter. It contains the latest stories published on our website from the last week. It goes out on Wednesday at Noon.

Check your inbox or spam folder to confirm your subscription.

Postal Annex Ad
Archive
Facebook X (Twitter) Instagram Bluesky TikTok
  • Terms of Use
  • Privacy
  • Accessibility
  • Ethics
  • Financials
  • Commenting
  • Business Directory
© 2026 ThemeSphere. Designed by ThemeSphere.

Type above and press Enter to search. Press Esc to cancel.

%d